Retirement Center in Gemeinde Schwyz
Project
- Construction of new replacement retirement center, demolition of the existing retirement and nursing home (consisting of three buildings)
- Infrastructure for 122 residents in the nursing care and dementia sections, including the general section, also accessible to the public and including rooms for use by third parties
- Landscaping
Helbling services
- Competition program incl. drawing up the operational concept and the room plan
- Drawing up the expert panel and the list of required specialists
- Organization and implementation of a public project competition, put out to tender in accordance with IVöB (Inter-cantonal agreement on public procurement)
- Profitability calculation
- Management of the adjudication process with final report
Key project figures
- Construction costs (Swiss building cost classification (BKP) 1 - 9: approx. CHF 40 million
- Duration of competition: 2010 - 2011
- Duration of construction owner representation: 2011 - 2014
- GFA approx. 13,500 m2
Customer: Gemeinde Schwyz