Von Roll Schweiz AG

Project
- Energy cost reduction in operation without self-financed investment
Helbling services
- Analysis at system level including determining potential and proposing measures
- Implementation of a measure by Helbling in contracting
- Helbling planned and invested
- Helbling carried the risk
- Online system monitoring and optimization over the Internet
- Operating time 4 years (1999 - 2003)
- The client is involved in the savings from the outset
Key project figures
- Construction costs: CHF 270,000
- Project duration: 6 month construction period, 4 year duration of contract
- Energy saving: approx. 450 kWth
- Cost saving: CHF 120,000 per year
- Period: 1998 - 2003
Customer: von Roll Schweiz AG