N4 National Highway, 6-lane Expansion Blegi-Rütihof

Project
- N04 national highway, Blegi-Rütihof section
- Lane expansion (high-capacity road) in both directions, from four lanes to six, restructuring of the Cham junction, improvement and new construction of engineering structures (underpasses, bridges), noise protection measures
Helbling services
- Construction owner role as general project manager during the maternity leave of the ASTRA general project manager from March to December 2010 Main tasks:
- Management of the project planning and implementation of the project
- Ensuring and coordinating the project planning, on schedule and within the cost specifications
- Supervision of the contracted project planning and building site offices and undertakings
- Ensuring the procurement process in line with statutory requirements
- Organization of the project administration
- Ensuring the flow of information and public relations work
Key project figures
- Investment costs: approx. CHF 200 million
- Project duration temporary general project manager: March 2010 - December 2010
- Construction period: approx. 2010 - 2012
Customer: Bundesamt für Strassen ASTRA