NEAT

 

Project
  • Lötschberg line incl. the Lötschberg Base Tunnel
  • Gotthard line incl. the Gotthard Base Tunnel and the Ceneri Base Tunnel 
  • Upgrading of additional stretches  (SBB, BLS, SOB, MGB, RhB)    

 

Helbling services   
  • Support for the FOT for project controlling at federal level
  • Updating and implementing the NEAT
  • Controlling Directive (NCD)  Performance, deadline and cost controlling, as well as reserve management 
  • Risk and quality management and testing at FOT level 
  • Assistance with progress reporting at FOT level 
  • Preparing and carrying out project tests 
  • Providing decision-making principles for change management 
  • Support for the Federal Department of the Environment, Transport, Energy and Communications plan approval processes 
  • Maintenance and further development of the FOT quality management system 
  • Assistance with periodic progress reports for politically responsible bodies 
  • Support for the start of operations    

Key project figures
 
  • Construction costs: approx. CHF 18 billion 
  • Duration of mandate: 1999 - 2009 

 

 

Customer: Federal Office of Transport (FOT)