ABB Turgi, Planning of Technical Infrastructure

Project  

  • Total renewal of the cooling infrastructure of the Turgi plant, media distribution as far as the test bays (“production”), planning of the infrastructure in the industrial plant construction   


Helbling services  

  • Preliminary study covering concept, analysis and selection of the location for the cooling infrastructure, estimate of costs, realization planning
  • Planning of all trades, i.e. HVAC, sanitation and electrics for the cooling infrastructure of the Turgi plant from the preliminary project to the implementation 
  • Dismantling and conversion work
  • Project management, specialist construction management, general contractor management 
  • Construction owner consultancy, user consultancy  

Key project figures  

  • Construction costs: CHF 4 million 
  • Lead time until commissioning: 8 months
  • Implementation: 2008 - 2009 

 

Customer: ABB Turgi