Project

  • Construction of a new tram line from Escher-Wyss Platz to Bahnhof Altstetten in Zurich  
  • Reconstruction of Pfingstweidstrasse SN 1.4.1    

 

Helbling services  

  • Representation of the chief site engineer for the overall management and coordination during the implementation
  • Comprehensive schedule and cost control 
  • Status report for the construction owner 
  • Procurement of the necessary contractor services 
  • Project risk analysis and specification of the key QA points 
  • Provision of the decision-making principles for the change system 
  • Support for public relations work  
  • Preparation of higher-ranking finance and budget plans 
  • Support for putting into operation   

 

Key project figures  

  • Construction costs: Approx. CHF 300 million 
  • Duration of mandate: 2008 - 2011 

 

Customer: Stadt Zürich, Tiefbauamt